2015-09-02 - 16728 - Spec - SNC No Work Order Process #SNCProject #sncsup

SPECIFICATIONS 2015-09-02 - Spec - 16728 SNC No Work Order Process


Purpose

Develop a Process for SNC in which there shall not be any Work Orders and the confirmations can be updated to ECC system.

Admin Info


Purpose
SNC No Work Order Process
Requested By
Jeffrey Mau
Spec Created By
Venkat/Adithya
Spec Created Date
09/02/2015
Spec QA by
Venkat/Adithya
Objects

Document Status
Closed - This option is not used in the Simplified WO Process

Estimates



Sl.No
Activity
Estimation in Hours
1
Research

2
Documentation

3
Development/ Config

4
Unit test in DEV

5
Unit test in QUA

6
Other activity


TOTAL

References

Prior Tickets

[Provide links of prior associated Spec / Break Fix BOSS document(s)]

Documents

[Attach any document(s) received for the requirement(s)]


Spec Changes


[List the changes made to program after the approval of the original requirement along with the Date on which the change request was received and the name of the initiator]

Sl.
Change Details
Requested By
Requested On
Notes if any










Functional Requirement


Purpose/WHY:

[Explain the purpose of the project and the reason why this requirement has come]

In Scope:

[List the activities to be included in scope]

Out of Scope:

[Out of scope activities]

Solution Summary


[Discuss this section with Requester and get approval prior to beginning work]

Test Plan
[List test scenarios/cases to be executed here]

Test ID
Test Scenario
Expected Results
SCM1
Full End to End Cycle shall be executed with different PO types
NB - Standard
NB- TAB
Z3NB - TAS
with combination of two vendors.
End to End cycle shall be executed be done correctly.Validation Reports-
  1. Both files created in ECC (PO Line file) and data in the .Net file should contain ALL records per filter criteria (all open POs)
  2. Records loaded in .NET should contain ALL records received from ECC
  3. Confirmations in .NET should be reflected in ECC Confirmations.
SCM2
Execute scenarios with multiple cycles to ensure PO statuses are updated correctly in ECC after each receipt from .NET
PO confirmations in ECC after each cycle should be correct.
SCM3
Check the ASN (Booking and Shipping) Files and validate it with and with out work order process
Booking and shipping files shall contain all the information when compared with work order and with out work order.
SCM4
Security check- User will try to enter PO which may or may not be part of their company
No EB POs Work Orders shall be seen in the ML Screen and vice versa
.Net Application testing.
Test ID
Test Scenario
Expected Results
001
Enter PO number and click on Apply
The PO details for the shall be displayed in the grid
002
Update the confirmations for the Phases by flagging and unflagging the check boxes and save
User should be able to check and uncheck the check boxes for the phase completed
and the data should be saved to database on Save click
003
Day End Process
User should be able to download the updated confirmations.
004
Ensure all Open PO Lines Received

PO_LINE file Testing
Test ID
Test Scenario
Expected Results
PO_LINE001
Run the PO_LINE file Job

1. ZE updated for all lines of a PO
2. ZE updated for all lines of a PO and any one line updated till ZP
3. ZE updated for all lines of a PO and all lines updated till ZP
4. ZE updated for all lines of a PO and any one line of a PO is deleted.
5. ZB updated for all lines of a PO
6. ZB updated for all lines of a PO and any line updated till ZP
7. ZB updated for all lines of a PO and all lines updated till ZP
8. ZB updated for all lines of a PO and any two lines of a PO is deleted
9. ZE&ZB updated for all lines of a PO
10. ZE&ZB updated for all lines of a PO and any line updated till ZP
11. ZE&ZB updated for all lines of a PO and all lines updated till ZP
12. ZE&ZB updated for all lines of a PO and any two lines of a PO is deleted
13. ZE&ZB updated for all lines of a PO and confirmations updated till ZN with delivery completion indicator.
14. ZE&ZB updated for all lines of a PO and confirmations updated till ZN.
15. ZE&ZB updated for all lines of a PO are updated with ZP.
16. ZE&ZB updated and all lines of a PO are updated till ZP with delivery completion indicator.
17. ZE&ZB updated and all lines of a PO are updated till ZS with delivery completion indicator.
18. ZE&ZB updated and all lines of a PO are deleted.
A file shall be placed in the application server.

1. All lines of the PO shall be there in the Downloaded file.
2. All lines of the PO shall be there in the Downloaded file with ZP updated for that line which for ZP is updated.
3. No Lines of the PO shall be there in the Downloaded file.
4. Excluding the deleted line all lines of the PO shall be there in the downloaded file.
5. All lines of the PO shall be there in the Downloaded file.
6. All lines of the PO shall be there in the Downloaded file with ZP updated for that line which for ZP is updated.
7. No Lines of the PO shall be there in the Downloaded file.
8. Excluding the deleted lines all lines of the PO shall be there in the downloaded file.
9. All lines of the PO shall be there in the Downloaded file.
10. All lines of the PO shall be there in the Downloaded file with ZP updated for that line which for ZP is updated.
11. No Lines of the PO shall be there in the Downloaded file.
12. Excluding the deleted lines all lines of the PO shall be there in the downloaded file.
13. All lines of the PO shall be there in the Downloaded file.
14. All lines of the PO shall be there in the Downloaded file.
15. No Lines of the PO shall be there in the Downloaded file.
16. No Lines of the PO shall be there in the Downloaded file.
17. All lines of the PO shall be there in the Downloaded file.
18. No Lines of the PO shall be there in the Downloaded file.
PO_LINE002
Download the file wide open

1. If any one line of a PO is active (with out delivery completion indicator or deletion)
2. If No Lines of the PO are updated with any phase.
3. If all lines of the PO are updated with all Phases till COM or the PO is closed
4. If All lines of the PO are mix of Open, Delivery complete & Deleted
All the Open POs and its corresponding lines must be downloaded in the file

1. All the Lines of that PO must be downloaded in the file.
2. All the Lines of that PO must be downloaded in the file.
3. No Lines of that PO must be downloaded in the file.
4. All the lines of that PO must be downloaded in the file.
Confirmations Program:

Test ID
Test Scenario
Expected Results
CNF001
Run the confirmations program
The confirmations which are updated from .Net application in the file are to be updated.



Solution Details


[Provide complete technical details for configuration or programming here]
Step 1: Generate the Open PO File from in ECC.


Step 2: Send the Open PO File to .Net Application.

Step 3: Browse the POs and Its lines in .Net Application and update the confirmations.




File 1:


Issues


[List Issues / Bugs identified in configuration or development]